ENGINEERING VENDOR TRANSITION SUPPORT

 

CLIENT

Leading Australian Industrial Producer

OBJECTIVE

Xenco led a structured transition program to manage the withdrawal of a long-standing engineering service provider from a large Queensland Coal port. Our role was to mitigate operational risk, safeguard institutional knowledge, and support a smooth shift to a more resilient and cost-effective service model.

THE CHALLENGES

The key challenges included:

  • Protecting 35+ years of engineering IP and project data to prevent rework or compliance issues.
  • Limited vendor network created risk of delays in maintenance and projects.
  • Tight transition timeline to avoid operational interruptions.
  • Ensuring accurate transfer of a large, complex dataset.
  • Rapidly identifying and securing reliable, cost-effective engineering vendors.

 

APPROACH

Xenco led a structured, phased transition program designed to mitigate risk, secure critical knowledge, and ensure operational continuity. The approach was governed through four key stages:

 

OUR RESULT

Xenco delivered a successful transition with significant, measurable outcomes:

  • Secured vendors, achieving 15–22% cost savings and keeping project costs well under budget.
  • Transferred and organised 157GB of critical data, preserving 35+ years of engineering knowledge with clear documentation.
  • Completed the transition on time with zero service interruptions while meeting all quality standards.
  • Built a vetted vendor network, improving procurement agility for future projects.
  • Delivered a full audit trail, demonstrating a structured approach to vendor transition and risk management.